Measurement Engineer

{ “@context”: “http://schema.org”, “@type”: “JobPosting”, “title”: “Measurement Engineer”, “description”: “

Responsibilities

Expected to:

  • Measure the works as they progress by taking surveys of the soil strip, cut, fill, capping, type 1, and surfacing.
  • Keeping a record of the stockpiles for materials going off-site.
  • Measurement of drainage works.
  • Measurement of subcontract works such as drainage, fencing and kerbing.
  • Identify, capture and forecast any variation to the scope such as the soft spots or changes with CBR values.

Qualifications

Have an understanding of:

  • Bills of Quantities
  • standard methods of measurement (CESMM4)
  • Groundworks/earthworks/drainage take-offs

Scope

  • Record the progress of works
  • Liaise with the commercial team
  • Provide quantities that will populate the monthly interim application
  • Provide quantities for certifying subbie payments
  • Forecast the remaining works (BOQ quantities)
  • Forecast remaining materials (if you want to pass that to someone)
  • Identify if we are going to exceed BoQ allowances

#J-18808-Ljbffr”, “datePosted”: “2026-04-25”, “hiringOrganization”: { “@type”: “Organization”, “name”: “RTL Group Ltd”, “sameAs”: “https://uk.whatjobs.com/pub_api__cpl__412973493__4861?utm_campaign=publisher&utm_medium=api&utm_source=4861&geoID=31” }, “jobLocation”: { “@type”: “Place”, “address”: { “@type”: “PostalAddress”, “addressLocality”: “City of Edinburgh” } } }
Company: RTL Group Ltd
Apply for the Measurement Engineer
Location: City of Edinburgh
Job Description:

Responsibilities

Expected to:

  • Measure the works as they progress by taking surveys of the soil strip, cut, fill, capping, type 1, and surfacing.
  • Keeping a record of the stockpiles for materials going off-site.
  • Measurement of drainage works.
  • Measurement of subcontract works such as drainage, fencing and kerbing.
  • Identify, capture and forecast any variation to the scope such as the soft spots or changes with CBR values.

Qualifications

Have an understanding of:

  • Bills of Quantities
  • standard methods of measurement (CESMM4)
  • Groundworks/earthworks/drainage take-offs

Scope

  • Record the progress of works
  • Liaise with the commercial team
  • Provide quantities that will populate the monthly interim application
  • Provide quantities for certifying subbie payments
  • Forecast the remaining works (BOQ quantities)
  • Forecast remaining materials (if you want to pass that to someone)
  • Identify if we are going to exceed BoQ allowances

#J-18808-Ljbffr…